| Location: | Malaysia |
|---|---|
| Owner: | MLNG Tiga Sdn Bhd |
| Lead Contractor: | Kellogg/JGC/Sime |
| Value: | US $4,800,000 |
| Peak Manpower: | 60 |
| Duration/Finish: | 21 months/2003 |
| Description: | Electrical & Instrument Commissioning Support for the MLNG Tiga, Bintulu |
Scope of Work:
Supervision of the Electrical and Instrumentation Commissioning scope of the New Train 3 and the tie-ins to the existing Train 1 and 2 facilities. The scope included Substations, MV and LV Distribution, DCS, Instrument Calibration and Loop-checking and the coordination of the Commissioning activities of the Major Package Vendors. Kentz Construction and Completion Management System (CCMS) was used throughout the site to coordinate completion of all electrical and instrumentation systems.