Delta 4 Power Station

 
 
Location:Nigeria
Owner:Nigerian National Petroleum Company (NNPC)
Lead Contractor:Marubeni  Corporation
Value:US$4,000,000
Peak Manpower:300
Duration/Finish:12 months/1989
Description:740 MW simple cycle power station
Delta 4 Power Station
Scope of Work:

Construction management, scheduling and planning, supervision, and construction services for the installation, testing, commissioning and start-up of the mechanical, electrical and instrumentation scope for the Delta 4 power station.

The scope included six 125MW general electric frame, nine gas turbine generator sets including all ancillary and balance of plant equipment.