Sakhalin 1 Russia

| Location: | Sakhalin Island |
|---|---|
| Owner: | Exxon Neftegas Ltd |
| Lead Contractor: | |
| Value: | US $50,000,000 |
| Peak Manpower: | 830 |
| Duration/Finish: | 24 months/2006 |
| Description: | EPC-1; EPC-2; EPC-4 Chayvo OPF Electrical & Instrumentation Construction and Commissioning De Kastri Completions and Commissioning and Project Management Support |
Scope of Work:
The OPF was constructed in 'modular' units in Korea and shipped directly to Chayvo in the summer shipping windows of 2005 and 2006. The balance of plant and services were 'stick-built'. The Oil Terminal at De Kastri was commissioned in two phases with initial focus on early export systems with balance of systems completed post hydrocarbon introduction.