Engen Cleanfuels Project, Durban

 
 
Location:South Africa
Owner:Engen Refinery
Lead Contractor:Fluor
Value:US $11,000,000
Peak Manpower:1,200
Duration/Finish:12 months lead up to shut, 4 week shut execution
Description:Maintenance Shutdown at Engen/Petronas Refinery with major project work.
Engen Cleanfuels Project, Durban
Scope of Work

Kentz maintenance and shutdown division were involved with the successful implementation of the Engen clean fuels projects and maintenance turnaround 2005. This included the prefabrication and construction of two major projects: The Dehexaniser and a major upgrade to the CHD (Catalytic Hydrotreater Desulphurizer) Unit.

The scope of work included MEIP (mechanical, structural, piping, electrical and instrumentation disciplines, the management and construction of the Dehex and CHD Projects and to plan and carry out the maintenance requirements during the turnaround (which took take place in September 2005). The maintenance portion began with scope verification and identification in March 2005 along with prefabrication of piping. In total the job consisted of two major projects (Dehex & CHD), the maintenance portion and thirteen small projects.