Pearl GTL Waste Water Treatment Plant
| Location: | Qatar |
|---|---|
| Owner: | Shell |
| Lead Contractor: | JGC-KBR |
| Value: | US $80,000,000 |
| Peak Manpower: | 500 |
| Duration/Finish: | 19 months/2008 |
| Description: | EPC scope for a modular Waste Water Treatment Plant for 35,000-man construction camp |

Scope of Work:
Project management, process design, detailed engineering, procurement, shipping, construction, testing and commissioning of the mechanical, piping, civil, electrical and instrumentation scope for the Waste Water Treatment Plant.
The project is logistically challenging with a tight execution schedule for the hydraulic system and the first WWT train. The process design is the responsibility of Qatar Kentz in conjunction with the technology supplier to meet the specified parameters for the influent at the primary lift station and treated effluent at the irrigation tank.