Trinidad LNG Expansion Project

 
 
Location:Trinidad
Owner:Atlantic LNG Company
Lead Contractor:Bechtel
Value:US $13,000,000/train
Peak Manpower:450
Duration/Finish:14 months/train (2006)
Description:Electrical and Instrumentation scope of New Trains 2, 3 and 4
Trinidad LNG Expansion Project
Scope of Work:       

Supervision, Installation, Pre-commissioning, Commissioning, and Testing  for the Electrical and Instrumentation scope of New Trains 2, 3 and 4 and the tie-ins to the existing Train 1 facility. The scope included Substations, HV and LV Reticulation, On-Plot Cabling, Control Equipment Installation, Instrument Installation, Calibration and Loop-checking. Kentz was awarded safety awards for its contribution towards safety excellence on the project.