Pearl GTL Temporary Telecoms

 
 
Location:Qatar
Owner:Shell
Lead Contractor:JGC-KBR
Value:US $12,896,929
Peak Manpower:105
Duration/Finish:12 months/2007
Description:Temporary Telecommunications for the Construction Site Camp for the Pearl GTL Project
Pearl GTL Temporary Telecoms
Scope of Work:

Project management, detailed engineering, procurement, supervision, installation, pre-commissioning, commissioning and testing of the Temporary Telecommunications scope.

The scope included copper cable network, fibre optic network, IDFs, MDFs, telecommunication cabinets and a SDH system compatible with the QTL network.

Data networks included PMC/EPCM CAN, Access CAN, Vendor CAN, Company CAN, WAN, IC Connectivity, IP Telephony Spur and a Camp Internet Café Facility.

The Systems scope included a Telephone System (1104 extensions), Tetra Radio System, Hotline (Incident Response) Communications, Satellite Phones, Mobile Phones, Wide General Alarm System, Pedestrian and Vehicular Access Control System, Surveillance (CCTV) System and a CATV System with 64 connections.