Pearl GTL Temporary Telecoms
| Location: | Qatar |
|---|---|
| Owner: | Shell |
| Lead Contractor: | JGC-KBR |
| Value: | US $12,896,929 |
| Peak Manpower: | 105 |
| Duration/Finish: | 12 months/2007 |
| Description: | Temporary Telecommunications for the Construction Site Camp for the Pearl GTL Project |

Scope of Work:
Project management, detailed engineering, procurement, supervision, installation, pre-commissioning, commissioning and testing of the Temporary Telecommunications scope.
The scope included copper cable network, fibre optic network, IDFs, MDFs, telecommunication cabinets and a SDH system compatible with the QTL network.
Data networks included PMC/EPCM CAN, Access CAN, Vendor CAN, Company CAN, WAN, IC Connectivity, IP Telephony Spur and a Camp Internet Café Facility.
The Systems scope included a Telephone System (1104 extensions), Tetra Radio System, Hotline (Incident Response) Communications, Satellite Phones, Mobile Phones, Wide General Alarm System, Pedestrian and Vehicular Access Control System, Surveillance (CCTV) System and a CATV System with 64 connections.