Sabah Power Station

| Location: | Malaysia |
|---|---|
| Owner: | Powertron |
| Lead Contractor: | Kentz |
| Value: | US $35,000,000 |
| Peak Manpower: | 100 |
| Duration/Finish: | 14 months/1998 |
| Description: | 120MW Simple Cycle Power Station (Turnkey Contract) |
Scope of Work:
Detailed Engineering, Supervision, Procurement, Installation, Testing, Commissioning and Start-up of a 120MW Power Station in Sabah.
The scope included 4 No. General Electric Frame 6 Gas Turbines, Distillate Oil Unloading, Oil Storage and Distribution, Gas Conditioning Plant, Gas Distribution, Fire Detection and Protection Systems, Turbine Washing System, RO Plant, Generator Transformers, Emergency Generator, 132kV Outdoor Switchgear consisting of 10 bays and 4 transformer bays, 11kV Switchgear, 415V MCCs, DCS including a TCP/IP Interface with the Mark V Control System, Control Room Equipment, Field Instrumentation. The scope also included the complete Civil and Building Works. The contract was awarded on a Turnkey basis.