PetroSA October 2009 Shutdown, GTL Plant & FA Platform

 
 
Location:South Africa
Owner:PetroSA
Lead Contractor:Petro SA
Value:US $8 million
Peak Manpower:800
Duration/Finish:6 months/December 2009
Description:Complete scope of services for the October 2009 shutdown at the refinery and reformer units of the GTL Plant and the FA platform offshore.
PetroSA October 2009 Shutdown, GTL Plant & FA Platform
Scope of Work

Scope development, prefabrication, preparation and planning for the October 2009 Shutdown at the GTL Facility in Mosselbay and the FA Platform located approximately 80km off the coast of Mosselbay, South Africa.

Scope of work includes mechanical maintenance including statutory and off-line works, electrical maintenance, instrumentation, piping repairs and vessel repairs. Work on over 172 pressure vessels, 140 heat-exchangers and fin-fans, 18 process columns and 1,072 valves.

The shutdown will be executed over a 26 day period starting at the end of September and finishing towards the end of October. Expected man-power to be involved is approximately 800 including indirect and direct field labour staff.