UPS Replacement for Control Room
| Location: | Secunda, South Africa |
|---|---|
| Owner: | Sasol Synfuels, duly represented by Sasol Technology |
| Lead Contractor: | Kentz Integrated Solutions |
| Value: | R 3,175,000 (US$ 396,875M) |
| Peak Manpower: | 20 |
| Duration/Finish: | 4 months/September 2009 |
| Description: | Brownfield’s project |
Scope of Work:
EPC of entire scope of work, which includes the following:
-Detail design of UPS system to be installed in the Refinery east basement
-Supply and install 100kVA UPS units with battery bank and battery stands
-Full testing of 100kVA UPS units before shipment to site, including total load and overload conditions
-Disconnection and removal of existing IPM 150kVA UPS units, associated panels, and equipment from the basement of the control room.
-Placement of new UPS equipment and associated equipment into the basement
-All rigging for adding and removing equipment from basement
-Supply and install all required cables, racking and earthing
-Disconnection, removal and disposal of existing batteries from control room basement. Supply of approved disposal certificate to Sasol Technology.