PPC Hercules Expansion Project
| Location: | PPC Hercules, Pretoria, South Africa |
|---|---|
| Owner: | PPC |
| Lead Contractor: | TWP |
| Value: | R92,375M (US$ 739,000M) |
| Peak Manpower: | 7 |
| Duration/Finish: | May 2007/December 2009 |
| Description: | Kentz Integrated Solutions is part of the TWP EPCM team performing the electrical and instrumentation design, engineering, procurement, quantity surveying, supervision and project management of the Hercules expansion project. |

Scope of Work:
The scope of work consists of the following:
The project is for a new vertical roller mill being constructed including the material handling and new clinker and cement despatch silos. The main mechanical contractor is Loesche.
New VRM substation
MV panels, MV cabling, transformers, power factor correction, LV reticulation, MCCs, lighting,earthing and lightning protection, HVAC, UPS, emergency generator, instrumentation, PLC and software development.