Ras Tanura Refinery Upgrade Package 5

 
 
Location:Saudi Arabia
Owner:Saudi Aramco
Lead Contractor:Bechtel / Kentz
Value:US $64,000,000
Peak Manpower:650
Duration / Finish:35 months / 1998
Description:Plant retrofit and expansion with modernisation of plant control and Monitoring systems.
Ras Tanura Refinery Upgrade Package 5
Scope of Work:

Detailed Engineering (Carried out In-Kingdom), Supervision, Procurement,  Material Supply, Installation, Testing and Commissioning for the Ras Tanura Refinery Upgrade Package 5. The Scope included the cut-over from the existing control systems to a new DCS (Honeywell TDC 3000 Ver 500) and the testing of the Control System for the following new facilities: NHT/CCR, Hydrocracker, Hydrogen Plant, Visbreaker, SuIphur/DGA, Waste Water Plant and High Pressure Boilers. Testing included SAT’s on the DCS, Triconex ESD, Bently Nevada VMS, CCC, DEC VAX, Gas Chromatographs, Enraf TGS, The total I/O count was 46,000.

S.A. Kent were awarded the Aramco 1st Place Ranking Safe Contractor of the Year 1997-1998.