LUN-A
| Location: | Sakhalin |
|---|---|
| Owner: | SEIC |
| Lead Contractor: | SEIC |
| Value: | US$ 395,000 |
| Peak Manpower: | 5 |
| Duration/Finish: | 2.5 months / Nov ‘09 |
| Description: | Commissioning of the Sakhalin Energy Investment Company (SEIC) offshore platform, located 15km off the north-eastern coast of Sakhalin Island. |

Scope of Work:
To provide specialist personnel to assist in the completion of the commissioning of SEIC Lun-A offshore drilling and production platform.
• Complete all hazardous area installation inspections.
• Verify Mechanical completion and pre-commissioning activities of construction contractor.
• Supervision of commissioning technicians to ensure commissioning systems / subsystems in line with client procedures and deadlines.
The LUN-A platform is designed for year round operation in harsh climatic conditions and is built to withstand rough seas, severe ice and high seismic activity.